Delivery times vary by configuration tier and are itemized in the quotation; vague commitments will not be accepted.
Standard Configuration
- Single pumps with standard materials (tool steel, 440C) and common displacements: 7–15 business days for shipment.
- Complete units including motor, gearbox, and base: add 3–5 business days for assembly and testing on top of the single pump lead time.
- Complete quantitative control or proportioning systems (including control cabinet and touchscreen): 20–30 business days, with control cabinet programming and integration testing accounting for roughly half of this period.
Factors Affecting Lead Time
- Special materials (Hastelloy, Stellite hardfacing, PTFE wetted parts) require outsourced sourcing, adding 10–20 business days.
- CE certification, explosion-proof certification, or third-party metrological calibration are scheduled based on the certifying body’s timeline and billed separately.
- Non-standard flow paths require drawing approval before production can begin; this confirmation period is included in the total lead time.
Rush Order Processing
Some commonly used displacements and materials are kept in stock; pump bodies can be shipped immediately to keep production lines running, with complete sets supplemented later. For project-based orders, we recommend locking in production schedules 45 days in advance to avoid conflicts during peak seasons.